Filton Avenue Infants School

Key Facts

Value:
£700k
Sector:
Programme:
22 Weeks
Scope of work:
Two extensions to the existing building over two phases, creating a new entrance area, additional group spaces and a much needed staffroom.

The works included the construction of two extensions to the existing building carried out over two phases.  The extensions created a new school entrance area, additional group spaces and a much needed staff room.

The school remained live with limited access to key areas of the site so logistical management and communication with the school was key to project success.

During the course of the project a number of large variations were added, including the complete refurbishment of the existing industrial kitchen.